Front desk at Construction Corps

By Matt Thompson, Owner and General Contractor at Construction Corps. U.S. Army combat veteran. Licensed general contractor since 2007, first in California; Florida licensed since 2022 (CGC, FBPE, EC, CFC, MRSR, MRSA). 35+ years in construction.

Last updated November 2026. Statutory timeframes are taken from the 2026 Florida Statutes: 553.792 (permit decision timeframes, as amended through HB 803, chapter 2026-63), 553.791 (private providers), 553.79 (permit expiration and the small-work exemption), and 713.13 and 713.135 (Notice of Commencement). County review times and the Express permit examples are from Pinellas County's Building Permit Review Times and Activity page; jurisdictions are from the county's Building Departments in Pinellas County page. Local review times change; confirm current figures with the jurisdiction. General information, not legal advice.

Key takeaways on Pinellas County permit timelines

- Florida law puts a decision clock on every local building department. For an applicant using the local government's plans reviewer, after the department receives a complete and sufficient application it must approve, approve with conditions, or deny within 5 business days for listed permit types on an existing single-family dwelling when the work is valued under $15,000, within 30 business days for residential units and listed permit types on structures under 7,500 square feet, and within 60 business days for structures of 7,500 square feet or more and for listed sign, nonresidential, multifamily, and site permits (FL Statute 553.792).
- Intake has its own clock. Within 5 business days of receiving an application, the local government must tell the applicant in writing what, if anything, is missing. If it does not, the application is deemed properly completed and accepted.
- A missed deadline costs the department money. The permit fee drops 10 percent of the original fee for each business day late, unless the parties agree in writing to a reasonable extension, the applicant caused the delay, or the delay comes from force majeure or other extraordinary circumstances. A timely written notice of specific code or ordinance problems avoids the reduction and gives the applicant 10 business days to revise; the department then has 10 business days to approve or deny, or the fee drops 20 percent per business day, unless the applicant agrees in writing to more time.
- Pinellas County publishes its actual first-review times on a dashboard refreshed daily for unincorporated Pinellas and its six partner communities, split into single-department reviews (such as interior remodels) and multi-department reviews (such as new construction and additions). Express permits, with examples including same-size window and door replacements, re-roofing, and like-for-like A/C change-outs, need no plan review and are usually issued the same day.
- With a private provider (FL Statute 553.791), the building official reviews the permit forms and documents for completeness only and must flag anything incomplete within 10 business days (5 for a single-trade plans review on a one- or two-family dwelling), or the permit is deemed approved and must be issued the next business day.
- Know your jurisdiction. Pinellas County permits unincorporated Pinellas plus Belleair Beach, Belleair Shore, Indian Rocks Beach, Kenneth City, Oldsmar, and Safety Harbor; Clearwater, St. Petersburg, Largo, Dunedin, Tarpon Springs, and other cities run their own building departments.

Ask five Tampa Bay contractors how long a permit takes in Pinellas County and you will get five confident, different answers, because they are answering different questions: which jurisdiction, which permit type, which review path, and, above all, whether the application was actually complete when it went in. This guide separates those questions. It covers the decision clocks Florida law now places on every local building department, where to check the review times Pinellas County actually publishes, the Express permit types that skip plan review, and the private provider option that moves plan review onto your schedule.

Construction Corps permits projects in Pinellas County, and permitting is part of our design-build delivery rather than something we hand back to the client. What follows is the map we use.

How Long Do Building Permits Take in Pinellas County?

It depends on three things: the permit type, the jurisdiction, and the review path. Florida law sets the outer bounds. Under FL Statute 553.792, for an applicant using the local government's plans reviewer, once the department receives a complete and sufficient application it must approve, approve with conditions, or deny within 5 business days for listed permit types on an existing single-family dwelling when the work is valued under $15,000, within 30 business days for residential units and listed permit types on structures under 7,500 square feet, and within 60 business days for larger structures and for listed sign, nonresidential, multifamily, and site permits. The department must also tell you within 5 business days if the application is incomplete, or it is deemed complete and accepted. At the fast end, Pinellas County Express permits need no plan review and are usually issued the same day. In between, actual first-review times vary with volume and complexity, and the county publishes current averages on a dashboard refreshed daily. With a private provider under FL Statute 553.791, plan review happens on your schedule and the building official's role is limited to a completeness check of the permit forms and documents, on a 10 business day clock (5 for a single-trade plans review on a one- or two-family dwelling).

1. The Statutory Clocks: What Florida Law Now Requires

The current decision deadlines in FL Statute 553.792 trace to HB 267 (2024). The Legislature amended the section again in 2026 with HB 803 (chapter 2026-63), which added the 5 business day tier for smaller work on existing single-family homes. Under the 2026 statute, a local government must approve, approve with conditions, or deny a building permit application within these timeframes after it receives a complete and sufficient application, unless the applicant waives them in writing. The local government may not require that waiver as a condition of reviewing the application, and a local ordinance may set shorter timeframes than the statute.

Decision Deadline Applies To
5 business days An existing single-family residential dwelling when the value of the work is less than $15,000: structural, accessory structure, alarm, electrical, gas, irrigation, landscaping, mechanical, plumbing, or roofing permits
30 business days Structures under 7,500 square feet: residential units (including a single-family residential unit or dwelling), accessory structure, alarm, electrical, irrigation, landscaping, mechanical, plumbing, or roofing permits
60 business days The same permit types for structures of 7,500 square feet or more
60 business days Signs, and nonresidential buildings under 25,000 square feet
60 business days Multifamily residential not exceeding 50 units; site-plan approvals and subdivision plats that do not require a public hearing or public notice; lot grading and site alteration
12 business days A site-specific building permit for an applicant using a master building permit under FL Statute 553.794
10 business days A single-family residential dwelling applied for by a Florida licensed contractor on behalf of an owner in a Community Development Block Grant-Disaster Recovery program, unless the application fails to satisfy the Florida Building Code or local laws or ordinances

Two more clocks run alongside the decision deadline. First, within 5 business days after receiving an application, the local government must give the applicant written notice of what information, if any, is needed to make the application properly complete under its published filing requirements. If it does not send that notice on time, the application is automatically deemed properly completed and accepted. Second, the fee penalty: if the local government misses a deadline, it must reduce the building permit fee by 10 percent of the original fee for each business day it is late, unless the parties agree in writing to a reasonable extension, the delay is caused by the applicant, or the delay is attributable to force majeure or other extraordinary circumstances.

The department avoids the reduction by sending a written notice, by email or U.S. mail and within the applicable timeframe, that states specifically why the application fails to satisfy the Florida Building Code or the local laws or ordinances. That notice must also tell the applicant it has 10 business days to submit revisions and that failing to correct the application in that window will result in denial. If the applicant submits revisions within the 10 business days, the department has 10 business days to approve or deny unless the applicant agrees in writing to a longer period. Miss that revision deadline and the fee drops 20 percent for each business day late.

The practical effect: the trigger for every clock is a complete and sufficient application measured against the department's published filing requirements. Read those requirements before you submit, and ask whether the department needs zoning, site, or utility approvals in place before it will accept the building application.

2. What Pinellas Actually Publishes, and Who Permits What

Pinellas County maintains a public Building Permit Review Times and Activity dashboard covering unincorporated Pinellas County and its six partner communities. The county says the data is refreshed daily, shows general trends only, and can be filtered to the last 30, 60, 90, or 120 days. Permits are grouped by complexity and by how many departments are involved: single-department reviews are limited reviews, such as interior remodels, that usually turn around faster; multi-department reviews are complex reviews, such as new construction or additions, that typically take longer. The headline figure is the typical first-review time, so treat it as the first review, not the full application-to-issuance timeline. Rather than quote a number here that will be stale by the time you read it, check the dashboard for the current figure.

The county also runs an Express permit lane. Express permits do not require plan review and are usually issued the same day. The county's examples include window and door replacements in the same size and location, re-roofing, garage door and water heater replacements, like-for-like A/C change-outs, and residential electrical service upgrades. Because they skip review, Express permits are not counted in the dashboard's review-time figures.

Jurisdiction is the other half of the answer. Pinellas County Building and Development Review Services issues permits for unincorporated Pinellas County, Belleair Beach, Belleair Shore, Indian Rocks Beach, Kenneth City, Oldsmar, and Safety Harbor. Other cities, including Clearwater, St. Petersburg, Largo, Dunedin, Tarpon Springs, Pinellas Park, and Seminole, run their own building departments with their own portals and intake rules, and some towns contract the work to a private firm. The same addition can face a different timeline a block away across a city line, and a mailing address can name a city the property is not in. The county recommends confirming which municipality a property is in through the Pinellas County Property Appraiser website (pcpao.gov) or the county's My Neighborhood lookup. The state clocks in Section 1 apply to every one of these local governments.

3. The Private Provider Option: Review on Your Schedule

FL Statute 553.791 lets a fee owner or the owner's contractor hire a private provider to perform building code plan review, inspections, or both, in place of the local building department. A private provider is a person licensed as a building code administrator under part XII of chapter 468, as an engineer under chapter 471, or as an architect under chapter 481. The mechanics that matter:

  • The review happens on your clock. The private provider reviews the plans for code compliance and signs the affidavit the statute requires, which is submitted with the permit application.
  • The building official gets a hard deadline and a narrow role. The local building official may review the private provider forms and documents for completeness only and must give the applicant written notice, stating specifically which forms or documents are incomplete, within 10 business days after receiving the application and the affidavit, or within 5 business days for a single-trade plans review on a single-family or two-family dwelling. If no notice goes out in time, the permit is deemed approved as a matter of law and must be issued the next business day. After revisions, the official has the remainder of the tolled period plus 5 business days, and any further review is limited to the issues in the original notice.
  • No second building code review. The local building official may not review plans the private provider has determined to be code compliant, except to the extent necessary to check local ordinances, floodplain management regulations, site review requirements, and other administrative or life safety review unrelated to building code compliance. Floodplain review stays with the local jurisdiction.
  • Inspections can move too. To use a private provider for inspections, the owner or contractor notifies the building official in writing at permit application, or by 2 p.m. local time 2 business days before the first scheduled inspection. After construction has started, the owner or contractor may still elect a private provider for a single-trade inspection on a single-family or two-family dwelling by giving notice before the next scheduled inspection. A private provider may not inspect a building designed or constructed by the provider or the provider's firm.
  • Local fees come down. The local jurisdiction must reduce the permit fee by the cost savings from not performing those services, and may not charge punitive administrative fees to an owner who chooses a private provider.
  • Occupancy has a clock as well. Once the applicant requests a certificate of occupancy or completion and presents the certificate of compliance, other required approvals, and payment of outstanding fees, the building official has 10 business days (2 business days for single-family or two-family dwellings) to issue it or identify incomplete documents, or the request is deemed granted the next business day.

Where the jurisdiction and scope allow it, Construction Corps uses private provider permitting with independent private providers. It pairs well with design-build delivery: the drawings, engineering, and product specifications come from one company, so the package the provider reviews is complete and consistent from the start.

4. The Lever You Control: A Complete Application on Day One

Every clock in this guide starts from the same trigger: a complete and sufficient application. A department that flags problems in writing on time stops the fee penalty, and a missed 10 business day revision window ends in denial. In our experience, the difference between a permit that moves and a permit that stalls is usually the package, not the reviewer:

  • Sealed structural engineering matched to the site's wind exposure and, where it applies, its flood zone.
  • Product approval documentation for every window, door, and roof assembly specified, current at submission.
  • Energy code documentation, plus any zoning, site, or utility approval the jurisdiction requires before it will accept the building application.
  • The Notice of Commencement plan: recorded before work starts and on file with the building department before the first inspection where the statute requires it. Our Florida lien law guide covers why that document matters beyond permitting.
  • A fast revision loop: when a department issues a written deficiency notice, the 10 business day revision window is a hard deadline.

This is where design-build delivery wins the permitting race. The people producing the drawings, the engineering, and the product specifications are the same company submitting and answering for the application, so completeness is designed in rather than chased after intake.

5. Planning Timelines by Project Type

Project Type How to Plan the Permit Phase
Express scopes (same-size windows and doors, re-roof, water heater, like-for-like A/C) In the county system, no plan review and usually same-day issuance. Express is the county's program; cities with their own building departments run their own processes, so ask.
Smaller work on an existing single-family home Listed permit types valued under $15,000 carry a 5 business day decision clock. Separately, a local government must exempt work valued under $7,500 on a single-family dwelling from the permit requirement when the owner or the owner's contractor submits a written request with the contract or other documentation showing the nature and value of the work; the exemption does not cover property partly or wholly in a flood hazard area or any electrical, plumbing, structural, mechanical, or gas work (FL Statute 553.79).
Interior remodel Usually a single-department review, the faster tier on the county dashboard. Statutory ceiling: 30 business days from a complete application for a structure under 7,500 square feet.
Addition or ADU Usually a multi-department review (building plus zoning, and floodplain where it applies). Plan around the dashboard's multi-department figure, the 30 business day ceiling for structures under 7,500 square feet, and at least one revision cycle. Private provider plan review can shorten the front end.
New custom build The full multi-department path, 30 or 60 business days by size once the application is complete. Site, zoning, and utility items can gate intake, so the calendar is won or lost before submission.
Coastal or flood zone projects Add floodplain review, which stays local even with a private provider, and where substantial improvement and substantial damage rules are applied (the 50 percent rule; unincorporated Pinellas and St. Petersburg use 49 percent). Front-load the flood analysis at design; it is the review most likely to generate comments.

If your project's schedule depends on a permit, plan the permit path at design, not after.

Call (727) 999-1855

6. Frequently Asked Questions

How long does a building permit take in Pinellas County?

Express permits, such as same-size window and door replacements, re-roofs, water heaters, and like-for-like A/C change-outs, need no plan review and are usually issued the same day in the county system. Reviewed permits vary by complexity and jurisdiction; Pinellas County publishes current first-review averages on a dashboard refreshed daily, split between single-department and multi-department reviews. Florida law sets the outer bound once an application is complete and sufficient, for an applicant using the local government's plans reviewer: 5 business days for listed permit types on an existing single-family home with work under $15,000, 30 business days for most residential permit types on structures under 7,500 square feet, and 60 business days for larger structures and listed sign, nonresidential, multifamily, and site permits (FL Statute 553.792).

What is Florida's permit timeline law?

FL Statute 553.792 requires a local government to approve, approve with conditions, or deny a building permit application within set business-day timeframes after it receives a complete and sufficient application. The current deadlines trace to HB 267 (2024), and HB 803 (chapter 2026-63) amended the section in 2026, adding a 5 business day deadline for listed permits on an existing single-family dwelling when the work is under $15,000. The statute also requires a written completeness notice within 5 business days and reduces the permit fee when a deadline is missed.

When does the permit clock actually start?

When the local government receives a complete and sufficient application. Within 5 business days of receiving an application, the department must tell you in writing what, if anything, is missing under its published filing requirements; if it does not, the application is deemed properly completed and accepted. If the department later sends a written notice of specific code or ordinance problems, you have 10 business days to submit revisions, or the application is denied.

What happens if the building department misses the deadline?

The permit fee comes down. Under FL Statute 553.792, the local government must reduce the building permit fee by 10 percent of the original fee for each business day it misses a deadline, unless the parties agree in writing to a reasonable extension, the applicant caused the delay, or the delay is due to force majeure or other extraordinary circumstances. No reduction is owed if the department sends a timely written notice stating specifically why the application fails the code or local rules. After revisions, the department has 10 business days to approve or deny, or the fee drops 20 percent for each business day late, unless the applicant agrees in writing to more time.

What is an Express permit in Pinellas County?

A permit that does not require plan review and is usually issued the same day. The county's examples include window and door replacements in the same size and location, re-roofing, garage door and water heater replacements, like-for-like A/C change-outs, and residential electrical service upgrades. Express permits are not counted in the county dashboard's review-time figures. Express is the county's program; cities with their own building departments run their own processes.

What is a private provider for permits?

Under FL Statute 553.791, a private provider is a licensed building code administrator, engineer, or architect hired by the owner or contractor to perform building code plan review, inspections, or both, in place of the local building department. The provider reviews the plans and signs the required affidavit. The building official then checks the forms and documents for completeness only and must flag anything incomplete within 10 business days (5 for a single-trade plans review on a one- or two-family dwelling), or the permit is deemed approved and must be issued the next business day. The official may not re-review plans the provider found compliant, except for local ordinances, floodplain management, site review, and other administrative or life safety review unrelated to building code compliance.

Is private provider permitting worth the cost?

When the schedule matters, often yes. Plan review happens on your timeline instead of the department queue, the building official's completeness check runs on a short statutory clock, and the local jurisdiction must reduce its permit fee by the cost savings from not performing those services, which offsets part of the provider's cost. It tends to matter most on multi-department projects and in post-storm backlogs. Floodplain and other non-building-code reviews still go through the local jurisdiction. Construction Corps uses independent private providers where the jurisdiction and scope allow.

Does Clearwater use the county building department?

No. Clearwater runs its own building department, as do St. Petersburg, Largo, Dunedin, Tarpon Springs, Pinellas Park, Seminole, and other cities. Pinellas County Building and Development Review Services issues permits for unincorporated Pinellas County, Belleair Beach, Belleair Shore, Indian Rocks Beach, Kenneth City, Oldsmar, and Safety Harbor. Confirm which municipality a property is in through the Pinellas County Property Appraiser website (pcpao.gov) or the county's My Neighborhood lookup before planning a schedule. The state decision clocks apply to all of them.

Do I need a Notice of Commencement for my permit?

For most projects, yes. Florida's lien law requires the owner or the owner's authorized agent to record a Notice of Commencement in the clerk's office before actually starting the improvement, except for improvements the statute exempts, and to post a certified copy or a notarized statement that it has been filed for recording, along with a copy (FL Statute 713.13). For a direct contract over $5,000, a copy must be filed with the permitting authority before the first inspection, and no further inspections can be performed or approved until it is (FL Statute 713.135); a direct contract to repair or replace an existing heating or air-conditioning system for less than $15,000 is excepted. Our Notice to Owner and Florida lien law guide covers why the document protects you beyond permitting.

How long is a building permit good for once issued?

For a single-family dwelling, Florida law says a permit issued by a local government expires 1 year after issuance or on the effective date of the next edition of the Florida Building Code, whichever is later, and the local government may extend it (FL Statute 553.79). The 9th Edition of the Florida Building Code takes effect December 31, 2026. A local government may also email or mail a notice of expiration at least 30 days before a permit expires. For other permit types, confirm the validity and extension rules with the building department; on long projects, tracking permit status is part of project management.

Permit strategy is schedule strategy

Construction Corps is a veteran-owned design-build general contractor based in Clearwater, serving Pinellas, Hillsborough, Pasco, and Sarasota counties. Permitting runs inside our delivery, not alongside it: the drawings, engineering, product approvals, and application package come from one company, complete on day one, with private provider permitting used where it saves real time.

If your project's schedule depends on a permit, the time to plan the permit path is at design. Bring us the project and we will map the jurisdiction, the review path, and a realistic calendar before you commit to a date.

Construction Corps, Inc.  |  2054 Weaver Park Drive, Clearwater, FL 33765
Phone: (727) 999-1855  |  Web: constructioncorps.com
Licenses: CGC1530192  |  FBPE39242  |  EC13013956  |  CFC1432954  |  MRSR5676  |  MRSA5772

About Construction Corps

Construction Corps, Inc. is a veteran-owned, full-service design-build general contractor headquartered at 2054 Weaver Park Drive, Clearwater, Florida 33765. Founded in 2022 and led by Matt Thompson, a U.S. Army combat veteran (Infantry, 11B) with 35+ years of construction experience, first licensed as a general contractor in California in 2007 and licensed in Florida since 2022, Construction Corps serves residential and commercial clients across the Tampa Bay region, including Pinellas, Hillsborough, Pasco, and Sarasota counties. The firm is an SBA-certified Service-Disabled Veteran-Owned Small Business (SDVOSB) and Veteran-Owned Small Business (VOSB), and is certified by the National Veteran Business Development Council (NVBDC) as a Service-Disabled Veteran-Owned Business (SDVOB). Construction Corps delivers design-build as one company, as full projects or plans first, holding Florida licenses CGC1530192 (general contractor), FBPE39242 (Florida Board of Professional Engineers), EC13013956 (electrical contractor), CFC1432954 (plumbing contractor), MRSR5676 (mold remediation), and MRSA5772 (mold assessor). Published project pricing is available at constructioncorps.com/estimator. Phone (727) 999-1855.

Sources Cited

Statutory timeframes are stated as of November 2026 from the 2026 Florida Statutes. Local review times change continuously; confirm current figures on the jurisdiction's published dashboard or with the building department. This article is general information, not legal advice or a schedule commitment for any specific project.

Back to top ↑


Back to Blog
Contact us media
Residential and Commercial Construction in Clearwater, Florida

Construction Corps is a family-run, veteran-owned, certified general contracting company with 35+ years of experience.

Contact us media
Accessibility: If you are vision-impaired or have some other impairment covered by the Americans with Disabilities Act or a similar law, and you wish to discuss potential accommodations related to using this website, please contact our Accessibility Manager at (727) 999-1855.