By Matt Thompson, Owner and General Contractor at Construction Corps. U.S. Army combat veteran. Licensed general contractor since 2007, first in California; Florida licensed since 2022 (CGC, FBPE, EC, CFC, MRSR, MRSA). 35+ years in construction.
Last updated October 2026. Review bodies, procedures, and fees are taken from the City of Tampa Architectural Review and Historic Preservation (ARHP) published documents and the design guidelines for each district posted on tampa.gov; the tax exemption from FL Statute 196.1997 (2026) and the city's program overview; the flood rule from 44 CFR 59.1. Where a document does not settle a point, this guide says to confirm it with ARHP. General information, not legal advice.
"Key takeaways on renovating in Tampa's historic districts
- Tampa has four local historic districts. The Architectural Review Commission (ARC) reviews Hyde Park, Seminole Heights, and Tampa Heights; the Barrio Latino Commission (BLC) reviews Ybor City. Most exterior work there needs a Certificate of Appropriateness (COA) before you submit for a building permit.
- There are two tracks. Staff can approve listed minor work without a hearing, including roof repair or replacement with approvable materials and no roofline change, wood fences that need no variance, exterior repairs with original or approved materials, and sheds and small additions of 150 square feet or less. Larger work goes to a public hearing after a required pre-application review and at least 30 days of mailed and posted notice.
- In Hyde Park, Seminole Heights, and Tampa Heights, the guidelines do not permit changing a window's size, pane pattern, or operation, or using jalousie, awning, or picture windows or reflective glass. Ybor City's guidelines have their own window rules.
- None of the four districts' guidelines accept vinyl, aluminum, or asbestos siding in place of original wood siding.
- City fees (2026 schedule): $100 for a COA, $30 for a residential staff approval, and $250 plus $0.01 per square foot for residential new construction or an addition of more than 40 percent of the original structure.
- Eligible historic buildings, including contributing structures and designated landmarks, can qualify for an exemption of up to 100 percent of the assessed value of qualifying improvements on City of Tampa and Hillsborough County taxes for up to 10 years, but Part I approval is required before any work starts and the city's program requires at least $10,000 in expenditures."
Tampa's historic neighborhoods are some of the most sought-after addresses in the region, and they come with a review step most owners have not been through before. A new window, a porch change, or a rear addition on a house in Hyde Park or Seminole Heights goes through historic review before it ever reaches the building department, and the rules are specific enough to change a design and a budget.
This guide covers the four local historic districts in the City of Tampa: Hyde Park, Seminole Heights, Tampa Heights, and Ybor City. It sets out which board reviews your property, how the Certificate of Appropriateness process works, what the design guidelines allow and do not allow on windows, siding, porches, additions, and equipment, what it costs, how the historic tax exemption works, and how historic status interacts with Tampa's flood rules. Our guide to building in Tampa and Hillsborough County covers the permit side of the same projects.
Do I need approval to renovate a house in a Tampa historic district?
Yes, for most exterior work. Under Chapter 27, Article II, Division 4 of the City of Tampa Code of Ordinances (Sections 27-95 and 27-113), the Architectural Review Commission and the Barrio Latino Commission approve or disapprove plans for alterations, demolitions, relocations, and new construction in the city's locally designated historic districts, landmarks, and other local historic designations. That approval is a Certificate of Appropriateness, and the city requires it before you submit to the Construction Services Division for plan review and permitting. The ARC covers Hyde Park, Seminole Heights, and Tampa Heights; the BLC covers Ybor City. Some minor work can be approved by staff without a public hearing; larger projects such as additions over 150 square feet and new construction go to a hearing. The Seminole Heights and Tampa Heights guidelines state that interior work and paint colors do not need a COA. Applications are filed through the city's Accela Citizen Access portal, and ARHP staff can be reached at (813) 274-3100, Option 3.
1. Which Board Reviews Your Property
| District | Review body | Guidelines and notes |
| Hyde Park | Architectural Review Commission (ARC) | Local historic district. Hyde Park Design Guidelines (current version posted on tampa.gov). |
| Seminole Heights | Architectural Review Commission (ARC) | Local historic district. Seminole Heights Design Guidelines, adopted by Ordinance 2002-21. |
| Tampa Heights | Architectural Review Commission (ARC) | Local historic district. Tampa Heights Design Guidelines (September 2000). |
| Ybor City | Barrio Latino Commission (BLC) | Local historic district with six subdistricts (YC-1 through YC-6) and separate industrial sector standards. Ybor City Design Guidelines, adopted by Ordinance 2003-0152. Confirm with ARHP that this is the current version. |
| Hampton Terrace, West Tampa, Palmetto Beach | Not ARC or BLC district review | Shown on the city's National Historic District maps, not its local district maps. The ARC and BLC review authority covers locally designated districts and landmarks, so National Register district status alone does not trigger a COA. An individually designated local landmark in these areas would still be reviewed. Confirm with ARHP. |
A third board, the Historic Preservation Commission (HPC), handles designation of districts and landmarks rather than COAs for construction. If you are not sure whether a property is in a local or a national district, the city's district maps page directs owners to call ARHP. Whether the building is contributing or non-contributing also matters: demolishing a contributing structure goes to a hearing, while demolishing a non-contributing structure is on the staff approval list, and only contributing buildings and designated landmarks qualify for the tax exemption.
Every review applies the district's design guidelines, the Secretary of the Interior's Standards for Rehabilitation, and the City Code. ARHP recommends contacting staff when you first consider a project, before drawings start.
2. How the Certificate of Appropriateness Process Works
| Staff (administrative) approval | Public hearing (ARC or BLC) | |
| Typical work | Residential: wood fences that need no variance; demolition of a non-contributing structure; roof repair or replacement with approvable materials and no roofline change; exterior repairs using original or approved materials; patios and slabs; paving; sheds and small additions of 150 square feet or less; appurtenant fixtures. Commercial adds signs that need no variance, storefront rehabilitation, street furniture, landscaping, and handicapped access. | Work that is not eligible for staff approval or that staff refers to the board, including new construction, larger additions, demolition of contributing structures, and variances. |
| Before you apply | Contact ARHP staff early to confirm the work qualifies. | Pre-application review with staff is required; it can occur once the project concept and a schematic design are ready. Staff review also occurs at a Historic Preservation Development Review and Compliance (HPDRC) meeting. |
| What to submit (in Accela) | Signed and notarized application (Exhibit A); notarized agent affidavit (Exhibit B) if an agent applies; digital elevations, site plans, and wall sections as applicable; material selections; any other information staff requires; fees paid. | Exhibits A and B; site plan at 1 inch = 10 feet; elevations at 1/4 inch = 1 foot; a wall section through a window at 3/4 inch = 1 foot or larger; details as required; a demolition plan for new construction or additions; first floor elevation for new construction; material selections and samples as required. Complete by the cycle's application deadline. |
| Notice | None listed. | Good Neighbor Notice sent by Certificate of Mailing to the owner (if the applicant is not the owner), owners within 300 feet, and participating neighborhood organizations, plus a posted sign on the property. All notice at least 30 calendar days before the hearing; the sign no more than 60 days before. Missed notice means the request is not placed on that cycle's agenda. |
| Schedule and outcome | Staff decision without a hearing. | The ARC and the BLC each have 12 public hearing cycles a year. After the hearing you receive a written decision, and the approved final drawings are uploaded in Accela to be stamped for the COA. |
Only the owner or an authorized agent may apply, and an agent needs a notarized affidavit signed by all owners. Plan the calendar around the hearing cycle: the pre-application review, a complete application by the cycle deadline, 30 days of notice, and the hearing all come before the building permit application can be filed. The COA is a separate approval from the building permit, not a substitute for it.
What it costs (ARHP fee schedule, 2026)
| Item | City fee |
| Certificate of Appropriateness | $100 |
| Staff approval | $30 residential; $75 commercial |
| New construction, or an addition of more than 40 percent of the original structure | $250 plus $0.01 per sq ft residential; $250 plus $0.02 per sq ft commercial |
| Demolition of a contributing structure | $250 plus $0.01 per sq ft residential; $750 plus $0.02 per sq ft commercial |
| Variance | $200 |
| Administrative appeal | $250 |
| Tax exemption application | $250 |
| Ybor City (BLC): balconies over right of way; encroachment signs; exterior painting | $500; $100; $50 |
| Continuance; extension of time; revision of a previous approval; determination letter (no ARC or BLC review required) | $25; $50; $25; $20 |
These are the historic review fees only. Building permit fees are charged separately by the Construction Services Division.
3. What Can and Cannot Change: The Rules by District
The four districts' guidelines share a common core, and the Hyde Park, Seminole Heights, and Tampa Heights guidelines follow the same structure with nearly identical wording on windows, siding, and foundations. Ybor City's guidelines are organized around its subdistricts and the BLC's ordinance review criteria. The table below compares the points owners ask about most, taken from each district's current guidelines on tampa.gov.
| Item | Hyde Park | Seminole Heights | Tampa Heights | Ybor City |
| Window replacement | COA required. Keep original size, pane pattern, and operation. Not permissible: jalousie, awning, or picture windows; reflective glass; replacing sound wood sash windows and frames. | COA required. Same size, pane pattern, and operation. Not permissible: jalousie, awning, or picture windows; reflective glass; metal sash in place of sound wood sash. | COA required. Same size, pane pattern, and operation. Not permissible: jalousie, awning, or picture windows; reflective glass; metal sash in place of sound wood sash. | Keep original size, shape, number of panes, and wood trim. No picture or louvered windows; no jalousie or other horizontal windows on commercial upper stories. |
| Siding | Vinyl, aluminum, or asbestos siding and vinyl or aluminum soffits not permitted. Match board size and exposure. | Replacing wood siding with vinyl, aluminum, or asbestos is not permissible. Match board size and exposure. | Replacing wood siding with vinyl, aluminum, or asbestos is not permissible. Match board size and exposure. | Aluminum, vinyl, or asbestos siding and stucco or composition covering are inappropriate. Match lap width. |
| Foundation enclosure | Not concrete, plywood, metal grating, or stucco. Repair or replace to match the original. | Not concrete block, plywood, metal gratings, or stucco. | Not concrete block, plywood, metal gratings, or stucco. | Avoid enclosing. If needed, wood or iron lattice or masonry; not flush concrete, plywood, stucco, or sheet metal. |
| Solar collectors | COA required. Recommended not visible from the front street. | COA required. Not permissible on the principal facade. | COA required. Not permissible where visible from the street. | Confirm with ARHP. |
| Air conditioning and equipment | The guidelines say no COA is required for air conditioners, antennas, or satellite dishes; locate outdoor AC units as far from the street as possible. | COA required for mechanical systems visible from the street or public right-of-way. No window or wall units on street facades. | Locate outdoor units as far from the street as possible. The guidelines conflict on window units on street facades; confirm with ARHP. | Confirm with ARHP. |
| Paint | The ARC offers paint and stain color suggestions; confirm with ARHP. | No COA required for paint colors. | No COA required for paint colors. | Color is one of the BLC review criteria, and the fee schedule lists a BLC exterior painting fee. Confirm before repainting. |
| Interior work | Confirm with ARHP. | No COA required. Staff may review interior drawings for exterior effect. | No COA required. Staff may review interior drawings for exterior effect. | Confirm with ARHP. |
Windows
Windows draw more questions than anything else. In Hyde Park, Seminole Heights, and Tampa Heights, any change, alteration, repair, replacement, or addition of windows, shutters, or awnings requires a COA before work starts. Staff may issue it if the work is deemed appropriate; otherwise the ARC decides at a public hearing. The guidelines call for repairing original windows where possible, retaining the wood trim around the opening, and, when replacement is necessary, filling the entire original opening with the same pane configuration. Lightly tinted glass may be acceptable but must be reviewed and approved by the ARC, and the Seminole Heights guidelines warn that tinted glass may affect federal tax incentive projects; the Tampa Heights guidelines name both federal tax credits and the local ad valorem tax exemption. The guidelines do not address impact-rated windows by name, so bring the product data, the pane pattern, and the operation type to ARHP before ordering.
Siding and exterior materials
Wood siding is the prevailing wall material in the ARC districts, and the guidelines direct owners to repair it or replace it with material that matches the original in board size, exposure, and trim, including full-width corner boards. Imitation brick and imitation stone are not permissible, and stucco is not to be added to surfaces that were not originally stuccoed. For new construction and additions, wood siding is preferred; artificial siding may be considered, but the specific material and profile must be approved by the ARC. Fiber cement siding is not named in any of the four guidelines, so its use on an addition or a contributing house is a question for ARHP, not an assumption.
Porches
Porches are treated as defining features. In Seminole Heights, enclosing a porch or porte cochere is not permissible unless the method preserves the original openness with an appropriately fitted transparent material and compatible details. Tampa Heights is stricter: enclosing a porch or porte cochere visible from the street is not permissible. Both guidelines prohibit removing a porch or porte cochere, in whole or in part, and suggest a compatible addition at the back of the house when more space is needed. In Ybor City, the guidelines say not to change a porch's size or configuration. For Hyde Park porch changes, confirm with ARHP before design.
Additions and new construction
All new construction and additions need a COA. Additions of 150 square feet or less are on the staff approval list; larger additions go to a public hearing, and a pre-application review with staff is required first. The guidelines review compatibility with the street and the original house through a set of design criteria that include scale, massing and building form, setback, orientation and site coverage, alignment and spacing, materials, trim and detail, facade proportions and window patterns, entrances and porch projections, roof forms, and quality of construction. In practice, that favors additions placed toward the rear, kept subordinate to the original house, and detailed so they read as compatible rather than copied. In Ybor City, the guidelines say metal buildings are inappropriate for new construction and will not be approved, and they advise consulting the BLC early in the schematic design phase.
4. The Historic Property Tax Exemption
FL Statute 196.1997 lets a county or city exempt up to 100 percent of the assessed value of improvements to historic properties that result from restoration, renovation, or rehabilitation, for up to 10 years. The City of Tampa (Ordinance 93-137, as amended by Ordinance 97-4) and Hillsborough County both participate, and the ARC or BLC reviews the applications. The exemption applies only to taxes levied by the government granting it, so it does not reduce taxes levied by other authorities, and it does not apply to taxes for bonds or to taxes approved by voter referendum.
| Requirement | What the program requires |
| Eligible buildings | Per the city's program overview: a designated local landmark listed in the National Register, a contributing structure in a designated local historic district, or a contributing structure in a National Register district. The Seminole Heights guidelines describe the City and County eligibility rules separately; confirm which exemption applies to your property with ARHP. |
| Minimum expenditure | $10,000. |
| Part I, Pre-Rehabilitation | Filed before construction with photographs, drawings, and material examples, plus the $250 application fee. The Property Appraiser performs a pre-rehabilitation assessment as the baseline. Reviewed at a public hearing, and approval is required before any demolition, construction, or alteration. |
| Part II, Post-Rehabilitation | Filed after substantial completion with photographs of the completed work. Reviewed at a public hearing, then presented to City Council and the Board of County Commissioners. |
| Standard | The Secretary of the Interior's Standards for Rehabilitation. The ARC or BLC bases its decision on the rehabilitation of exterior and interior features. |
| Covenant and term | The owner signs a covenant with the City and County to maintain the improvements for the full exemption period. The exemption takes effect January 1 following substantial completion and remains in effect through a change in ownership, as long as the historic character and qualifying improvements are maintained. |
The timing is the trap. Part I must be approved before work begins, so an owner who starts a rehabilitation and asks about the exemption later has already lost it for that work. Interior work counts too: the Seminole Heights and Tampa Heights guidelines note that changes to significant interiors may affect the ad valorem exemption and federal tax credits, even though interior work does not need a COA there. We are a contractor, not a tax advisor; confirm eligibility and the tax effect with ARHP, the Hillsborough County Property Appraiser, and your tax professional.
5. Historic Status and Tampa's Flood Rules
If a home in one of these districts sits in a FEMA Special Flood Hazard Area, the 50 percent substantial improvement rule is in play. The federal definition of substantial improvement (44 CFR 59.1) excludes any alteration of a historic structure, provided the alteration will not preclude the structure's continued designation as a historic structure. The same section defines a historic structure as one that is listed individually in the National Register (or preliminarily determined eligible), certified or preliminarily determined as contributing to a registered historic district, individually listed on an approved state inventory, or individually listed on a local inventory in a community whose preservation program is certified by an approved state program or the Secretary of the Interior.
Two cautions. First, being inside a local historic district does not by itself make a building a historic structure under that definition; the building has to fit one of the four categories. Second, how the City of Tampa applies the exclusion to a specific project is a determination for the city's floodplain administrator in the Construction Services Division, and the COA and the flood review are separate approvals. Confirm both before design, especially on a large rehabilitation or an addition where the 50 percent threshold would otherwise be in play.
6. What We Check Before Design Starts
| Check | Why it matters in a Tampa historic district |
| District and review body | Local district or National Register only; ARC or BLC. This decides whether a COA is needed and which guidelines apply. |
| Contributing status | Affects demolition review, tax exemption eligibility, and whether the federal historic structure definition may apply to flood review. |
| Staff track or hearing | Staff-eligible work can move quickly. Hearing work needs a pre-application review, a complete application by the cycle deadline, and 30 days of notice before the hearing. |
| Windows, siding, and porch scope | Product choices that fail the guidelines are better caught before ordering than at the hearing. |
| Tax exemption | If the owner wants the exemption, Part I has to be filed and approved before any work starts. |
| Flood zone and structure value | Sets whether the 50 percent rule is in play and whether the historic structure exclusion needs a city determination. |
| Zoning | Setbacks, lot coverage, and height still apply. A variance adds a separate review and fee. |
This is where design-build earns its keep in a historic district. The guideline review, the COA, and the permit design are one sequence, so we work through the district rules and the hearing calendar before drawings are finished, and the plans that go to ARHP are the plans that get built. The majority of the plans we produce for homeowners go on to be built by us. We also produce plans for other contractors, who build those projects themselves. Published project pricing is available at constructioncorps.com/estimator.
7. Frequently Asked Questions
Do I need a Certificate of Appropriateness to replace windows in Hyde Park?
Yes. Any change, alteration, repair, replacement, or addition of windows, shutters, or awnings in Hyde Park requires a COA before work starts. Staff may approve appropriate replacements; other requests go to the Architectural Review Commission. The Hyde Park guidelines require replacements to fill the original opening with the same pane configuration and do not permit changing the window's size or operation, jalousie, awning, or picture windows, reflective glass, or replacing sound wood sash windows and frames.
Can I put vinyl or fiber cement siding on a historic house in Tampa?
Not vinyl. None of the guidelines for Hyde Park, Seminole Heights, Tampa Heights, or Ybor City accept vinyl, aluminum, or asbestos siding in place of original wood siding, and replacement wood should match the original board size and exposure. Fiber cement is not named in any of the four guidelines. On new construction and additions, the ARC districts allow artificial siding to be considered if the specific material and profile are approved, so confirm any fiber cement product with ARHP before specifying it.
Which board reviews renovations in Ybor City?
The Barrio Latino Commission (BLC) reviews Certificates of Appropriateness in the Ybor City Historic District, using the Ybor City Design Guidelines, the Secretary of the Interior's Standards for Rehabilitation, and the City Code. Hyde Park, Seminole Heights, and Tampa Heights are reviewed by the Architectural Review Commission (ARC). Both boards are staffed by the City of Tampa's Architectural Review and Historic Preservation office, (813) 274-3100, Option 3.
Can city staff approve my historic district project without a hearing?
For listed minor work, yes. The City of Tampa staff approval list for residential properties includes wood fences that need no variance, demolition of a non-contributing structure, roof repair or replacement with approvable materials and no roofline change, exterior repairs with original or approved materials, patios and slabs, paving, sheds and small additions of 150 square feet or less, and appurtenant fixtures. Other work goes to an ARC or BLC public hearing after a required pre-application review.
How much does a Certificate of Appropriateness cost in Tampa?
Under the City of Tampa's 2026 ARHP fee schedule, a Certificate of Appropriateness is $100, a residential staff approval is $30, a variance is $200, and residential new construction or an addition of more than 40 percent of the original structure is $250 plus $0.01 per square foot. Building permit fees are separate.
Do I need approval to paint a house in a Tampa historic district?
It depends on the district. The Seminole Heights and Tampa Heights guidelines state that paint colors do not require a Certificate of Appropriateness. The Hyde Park guidelines treat paint and stain colors as suggestions from the ARC. In Ybor City, color is one of the Barrio Latino Commission's review criteria and the city's fee schedule lists a BLC exterior painting fee, so confirm with ARHP before repainting there.
Can I add onto a contributing house in Seminole Heights?
Yes, with a Certificate of Appropriateness. Additions of 150 square feet or less may be approved by staff; larger additions go to an Architectural Review Commission public hearing after a required pre-application review and 30 days of mailed and posted notice. The ARC reviews scale, massing, setback, materials, roof form, and window patterns for compatibility, and the Seminole Heights guidelines suggest a rear addition rather than enclosing a front porch when more space is needed.
Is there a tax break for renovating a historic home in Tampa?
Yes. Under FL Statute 196.1997 and City of Tampa Ordinance 93-137, as amended, eligible historic properties can receive an exemption of up to 100 percent of the assessed value of qualifying improvements on City of Tampa and Hillsborough County taxes for up to 10 years. The city's program requires at least $10,000 in expenditures, work meeting the Secretary of the Interior's Standards, and Part I approval at a public hearing before any work begins.
Does the FEMA 50 percent rule apply to historic houses in Tampa?
The federal definition of substantial improvement in 44 CFR 59.1 excludes alterations of a historic structure that do not preclude its continued historic designation, but only buildings that meet the federal definition of a historic structure qualify, such as those individually listed in the National Register or certified as contributing to a registered historic district. Location in a local district alone is not enough. Confirm how the City of Tampa applies the exclusion to your building with the Construction Services Division before design.
Who designs and builds renovations in Tampa's historic districts?
Construction Corps is a veteran-owned design-build general contractor based in Clearwater that designs and builds additions, remodels, and renovations across Hillsborough, Pinellas, Pasco, and Sarasota counties, holding Florida licenses CGC1530192, FBPE39242, EC13013956, CFC1432954, MRSR5676, and MRSA5772. Call (727) 999-1855.
Start with the district rules, not the drawings
Construction Corps is a veteran-owned design-build general contractor based in Clearwater, serving Hillsborough, Pinellas, Pasco, and Sarasota counties. Before we draw anything in a Tampa historic district, we confirm the district and review body, the building's status, which work can go to staff and which needs a hearing, and how the flood rules apply, so the design and the budget fit the review from the start.
Planning a renovation or addition in Hyde Park, Seminole Heights, Tampa Heights, or Ybor City? Bring us the address, photos of the house, and any survey or Elevation Certificate you have.
- Construction Corps, Inc. | 2054 Weaver Park Drive, Clearwater, FL 33765
- Phone: (727) 999-1855 | Web: constructioncorps.com
- Licenses: CGC1530192 | FBPE39242 | EC13013956 | CFC1432954 | MRSR5676 | MRSA5772
About Construction Corps
Construction Corps, Inc. is a veteran-owned, full-service design-build general contractor headquartered at 2054 Weaver Park Drive, Clearwater, Florida 33765. Founded in 2022 and led by Matt Thompson, a U.S. Army combat veteran (Infantry, 11B) with 35+ years of construction experience, first licensed as a general contractor in California in 2007 and licensed in Florida since 2022, Construction Corps serves residential and commercial clients across the Tampa Bay region, including Pinellas, Hillsborough, Pasco, and Sarasota counties. The firm is an SBA-certified Service-Disabled Veteran-Owned Small Business (SDVOSB) and Veteran-Owned Small Business (VOSB), and is certified by the National Veteran Business Development Council (NVBDC) as a Service-Disabled Veteran-Owned Business (SDVOB). Construction Corps delivers design-build as one company, as full projects or plans first, holding Florida licenses CGC1530192 (general contractor), FBPE39242 (Florida Board of Professional Engineers), EC13013956 (electrical contractor), CFC1432954 (plumbing contractor), MRSR5676 (mold remediation), and MRSA5772 (mold assessor). Published project pricing is available at constructioncorps.com/estimator. Phone (727) 999-1855.
Sources cited
- City of Tampa, Architectural Review and Historic Preservation main page, Architectural Review Commission, Barrio Latino Commission, and Historic Preservation Commission pages: tampa.gov/historic-preservation
- City of Tampa, Historic District Maps (local and national districts): tampa.gov/historic-preservation/info/district-maps
- City of Tampa, Architectural Review Commission / Barrio Latino Commission Application Submission Requirements (staff approval, public hearing, public notice, post-hearing), citing City Code Chapter 27, Sections 27-95, 27-113, and 27-149(c): tampa.gov
- City of Tampa, Architectural Review Commission and Barrio Latino Commission Fee Schedule (2026): tampa.gov
- City of Tampa, Hyde Park Design Guidelines; Seminole Heights Design Guidelines (Ordinance 2002-21); Tampa Heights Design Guidelines (September 2000); Ybor City Design Guidelines (Ordinance 2003-0152, revised February 2003): tampa.gov
- City of Tampa, Historic Property Ad Valorem Tax Exemption Program overview (Ordinance 93-137, as amended by Ordinance 97-4): tampa.gov
- FL Statute 196.1997 (2026), Ad valorem tax exemptions for historic properties: flsenate.gov
- 44 CFR 59.1, definitions of historic structure and substantial improvement: ecfr.gov